Application Process for Construction of an Infrastructure Project

To qualify for tax credits for constructing an infrastructure project, a person or qualified company must follow the process described below.

  • Apply for program incentives by completing an 2009 Initial Application for each project and submit it to Commerce. (See Sections 21 and 22 of the Program Guidelines for more detail.)
  • Within 30 days of receipt of a complete application, Commerce will notify the company of pre-approval or denial. If a company is pre-approved, Commerce will issue a Letter of Qualification (effective until completion of the project) to the company and transmit a copy to the Arizona Department of Revenue.

Next Steps:

  • Within 90 days of the pre-approval date an infrastructure applicant must demonstrate it has begun construction on either the soundstage or support and augmentation facility. (See Section 23 of the Program Guidelines for more detail.)
  • An infrastructure applicant must document continuing eligibility within 12 months and 36 months of the pre-approval date.

Upon Completion of Construction:

  • Within 30 days of completion of construction of an infrastructure project, the applicant must submit a Completion Report to Commerce. (See Section 24 of the Program Guidelines for more detail.)
  • Commerce may issue post-approval to the applicant after reviewing the Completion Report and verifying the applicant’s eligibility.
  • Once post-approval is received the applicant may claim the tax credits.